§ 38-230. Conditions or permits.
(a)
The city may grant a permit to discharge to persons meeting all requirements of section 38-229 provided that the person:
(1)
Submit an application within 30 days after the effective date from which this article is derived on forms supplied by the approving authority;
(2)
Secure approval by the approving authority of plans and specifications for the facilities when required;
(3)
Has complied with all requirements for agreements or arrangements, including, but not limited to, provisions for:
a.
Payment of charges;
b.
Installation and operation of the facilities and of pretreatment facilities, if required;
c.
Sampling and analysis to determine quantity and strength when directed by the city; and
(4)
Provides a sampling point, when requested by the city, subject to the provisions of this article and approval of the approving authority.
(b)
A person applying for a new discharge shall:
(1)
Meet all conditions of subsection (a) of this section; and
(2)
Secure a permit prior to discharging any waste.
(Code 1968, § 20-103; Ord. No. 440, § 18, 10-21-1980)